NB/T 25013-2013
Test requirements for generator unit first synchronization of nuclear power plant (English Version)

Standard No.
NB/T 25013-2013
Language
Chinese, Available in English version
Release Date
2013
Published By
Professional Standard - Energy
Latest
NB/T 25013-2013
Scope
This standard specifies the main test items and test requirements for a new (expanded) pressurized water reactor nuclear power plant from the pre-start inspection of the generator to the completion of the generator's simultaneous connection to the grid. This standard is applicable to the first grid connection test of pressurized water reactor nuclear power plant generating units.

NB/T 25013-2013 history

  • 2013 NB/T 25013-2013 Test requirements for generator unit first synchronization of nuclear power plant
Test requirements for generator unit first synchronization of nuclear power plant



Copyright ©2024 All Rights Reserved