5.1.1 The garbage pile should be excavated in zones, units, and layers, and each excavation area should be numbered. 5.1.2 Corresponding prevention and control measures should be taken during the entire excavation and screening process. 5.1.3 Archiving work should be done throughout the entire excavation and screening process. 5.2.1 Site survey 5.2.2 Develop excavation plan 5.2.3 Slope treatment 5.2.4 Ventilation pretreatment 5.2.5 Groundwater pollution control 5.2.6 Leachate drainage and treatment 5.2.7 Screening workshop construction 5.3 Excavation 5.4 Screening 5.5 Utilization and disposal of screened materials 5.6 Storage and transportation 5.7 Site restoration
T/ZAEPI 003-2022 history
2022T/ZAEPI 003-2022 Technical code for excavation and screening of municipal solid waste landfill