1. Related terms. Focus on explaining the scope of this specification, references to normative documents and definitions of related terms. 2. Main inspection contents. 1. Before periodic inspection, the user should make the following preparations. 2. 2.1 The general inspection procedures include pre-inspection preparation, tank inspection, defect and problem handling, inspection result summary, inspection conclusion and issuance of inspection report, etc. According to the requirements, the inspection personnel can determine the inspection items and carry out the inspection work according to the actual situation. 2.2 Inspection items 2.3 Document review 2.4 Appearance inspection 2.5 Structural inspection 3. Non-destructive testing 4. Overall pressure (leakage) test 5. Inspection conclusion
T/CFLP 0037-2022 history
2022T/CFLP 0037-2022 Inspection rules for atmospheric pressure metal tank of road tank-vehicle for liquid dangerous goods transport