This document specifies the start-up trial operation test procedures and requirements for impulse turbine generator units with a single unit capacity of 5 MW and above and a runner diameter of 1.0 m and above. This document is applicable to the start-up trial operation test and handover acceptance of the impulse turbine generator set and related equipment of the hydropower station.
DL/T 2578-2022 history
2022DL/T 2578-2022 Start-up test procedures for impact turbine generator sets